Site: Daily Reports, Delays and Crews ​

The Site menu is the site diary of your projects. Every working day, the site team writes a Daily Site Report: who was on site, what work was done, which plant was used, the weather and anything that happened (delays, visits, inspections). Once a manager approves the report, Odoo updates the progress of the schedule, records the labour hours as timesheets and logs the plant hours.

WHERE AND WHO

Menu: ConstructionSite, with three sub-menus: Daily Site Reports, Delay and Event Log and Crews.
Users: the Site Supervisor / Foreman and the Site Engineer write the reports; the Site Manager or the Project Manager approves them. On a phone or tablet, the same report can be written in the Site App.

Daily Site Reports ​

A daily site report (also called a site diary or daily log) is one record per project and per day. If a big project has several work fronts, you can write one report per Area (for example Tower B or Villas 19 to 24).

A report goes through three stages:

Draft→Submitted→Approved
  • Draft: the site team fills in the report. It can be changed freely.
  • Submitted: the report is finished and waits for approval. It can no longer be changed.
  • Approved: the manager checked it. The work done, labour hours and plant hours are now taken into account by the rest of the system.

Create a daily report ​

  1. Go to ConstructionSiteDaily Site Reports. The list shows the latest reports first, with the manpower, man-hours, hours lost and the stage. Click New.

    List of daily site reports
    The list of daily site reports. The New button is framed.
  2. Choose the Project in the big field at the top. The Date is today by default; change it if you write the report of another day. If the project has several work fronts, type the Area.

    New daily site report with project, date and area
    A new report: project, date and area are filled in.
    FieldWhat to enter
    ProjectThe construction project. Only construction projects are listed.
    DateThe day the report is about (default: today).
    AreaOptional. Building, zone or work front, when the project has several reports a day.
    Working HoursThe normal hours of the day (default 8:00). Odoo proposes them for each worker.
    Prepared ByYou, by default.
    Weather, Temperature (°C), Weather RemarksSunny, Rain, Sandstorm, Extreme Heat... the minimum and maximum temperatures, and any remark (for example a midday break in summer).
  3. Fill in the tabs in the lower half of the form, as explained below: Manpower, Work Done, Plant, Delays and Events, Photos and Remarks. The totals above the tabs (Own Workforce, Subcontractors, Man Hours, Hours Lost) are calculated automatically.

ONE REPORT PER DAY AND AREA

A project can have only one report per day for the same area. If you try to create a second one, Odoo shows the message "... already has a report on ... for this area." Open the existing report instead, or type a different Area.

Manpower tab ​

The Manpower tab lists who worked on site: your own workers one by one, and the subcontractor crews by headcount.

  1. Click Load Crews. Odoo adds every member of the project's crews: your own workers with their usual activity and the normal working hours, and each subcontractor crew with its usual headcount. If a worker checked in that day (for example with Crew Attendance in the Site App), the Attendance hours are filled in and used as the hours worked.

    Manpower tab after Load Crews
    The Manpower tab after clicking Load Crews (framed): seven own workers and one subcontractor crew of 14.
  2. Correct the lines if needed: change the Activity a worker was on, the Hours and the Overtime. Click the bin icon to remove a worker who was absent. Click Add a line to add a worker or a subcontractor who is not in a crew.

    ColumnWhat it means
    TypeOwn Workforce (choose the Employee) or Subcontractor (choose the Subcontractor company and type the Headcount).
    ActivityThe schedule activity (task) the people worked on.
    Hours / OvertimeNormal and overtime hours of the day. Man Hours = headcount × (hours + overtime).
    Cost Code (hidden column)Optional. The cost code of the hours; by default the labour cost code.

Work Done tab ​

Here you record the progress of each activity of the schedule. This is what moves the progress bar of the Planning.

  1. Open the Work Done tab and click Add a line. Choose the Activity and type the Location (level, zone, grid).

  2. Enter the progress:

    • if the activity has a Planned Quantity (for example 12 t of steel), type the quantity Done Today;
    • if it has no planned quantity, type the Progress to Date (%): the total progress of the activity after today, not the progress of the day.
    Work Done tab
    0.8 t done today on the first floor slabs (planned 12 t), and 90% reached on the excavation of villas 13 to 24.

Plant tab ​

  1. Open the Plant tab and add one line per machine. For your registered plant, choose it in Registered Plant: its name is filled in for you. For any other machine (for example a hired water tanker), leave Registered Plant empty and type its name in Plant.

  2. Type the Hours Worked, Hours Idle (on site but not working) and Breakdown Hours, and optionally the Activity and a Note.

    Plant tab
    Two registered machines and one hired water tanker.

TIP

Always choose the Registered Plant when the machine is in the Plant Register: when the report is approved, Odoo creates and confirms a Plant Log for it, which moves its hour meter and charges its hire to the project.

Delays and Events tab ​

  1. Open the Delays and Events tab and add one line per event. Choose the Type (Delay, Site Instruction, Inspection, Visitor, Delivery, Safety, Other) and describe what happened.

  2. For a delay, choose the Responsible Party (Client / Engineer, Contractor, Subcontractor, Weather, Authority / Utility, Other), the Activity affected and the Hours Lost.

    Delays and Events tab
    A delay caused by the consultant (2 hours lost) and a client visit.

WHY IT MATTERS

Delays recorded day by day, with the party responsible, are your evidence for an extension of time claim. They are all listed in the Delay and Event Log.

Photos and Remarks tabs ​

In the Photos tab, click Photos to upload pictures of the day. In the Remarks tab, write general remarks, instructions received, or the plan for tomorrow.

Photos tab
The Photos tab: click the button to upload pictures.

Submit and approve the report ​

  1. When the report is complete, click Submit. The stage becomes Submitted and the report can no longer be changed.

    Submit button
    A draft report: the Submit button is framed.
  2. The site manager or project manager finds the reports waiting for approval with the To Approve filter of the search bar.

    Reports to approve
    The To Approve filter lists the submitted reports.
  3. The manager opens the report, checks it and clicks Approve.

    Approve button
    A submitted report: the Approve button is framed.
  4. The stage becomes Approved and Approved By shows the manager. A new Timesheets tab lists the hours of your own workers.

    Approved report with timesheets
    The approved report and its timesheets.

What the approval does ​

Part of the reportEffect of the approvalWhere to see it
Work DoneThe Progress (%) of each activity is recalculated from all its approved reports: quantity done ÷ planned quantity, or the last percentage reported.The activity in PlanningSchedule, tab Planning
Manpower (own workers)One timesheet per worker, on the project and the labour cost code. Their cost becomes an actual cost of the project.The Timesheets tab of the report; Cost Control
Plant (registered)One confirmed plant log per machine: the hour meter moves and the internal hire is charged to the project.PlantPlant Logs
Activity progress updated by the daily reports
The activity "First floor slabs and beams": 2 t done out of 12 t planned, so the progress is 17%. The list shows each daily report that contributed.
Plant logs created by the report
The two plant logs of Oct 30 were created and confirmed by the approval. The excavator, which is owned, gets a hire charge.

CORRECTING AN APPROVED REPORT

Click Reset to Draft to reopen a submitted or approved report. For an approved report, Odoo removes its timesheets and plant logs, and the progress of its activities goes back to the previous reports. Correct the report, then submit and approve it again. An approved report cannot be deleted: reset it to draft first.

Calendar and reminders ​

Use the view buttons at the top right of the list to switch to the Kanban or the Calendar view. The calendar shows at a glance the days without a report.

Calendar of daily site reports
The calendar view of the daily site reports.

MISSING REPORTS

Every morning, Odoo checks the projects in construction. If yesterday was a working day and no report was written, the project manager receives a to-do activity "Daily site report of ... missing". The project form also has a Daily Reports smart button that lists the reports of that project.

Delay and Event Log ​

This menu lists all the events recorded in the daily reports of all projects, in one place. You cannot create events here: they always come from a daily report.

  1. Go to ConstructionSiteDelay and Event Log. By default the Delays filter is on. Remove it (click ×) to see all the events: visits, inspections, deliveries...

    Delay and Event Log
    The delays of all the daily reports, with the hours lost.
  2. To prepare an extension of time claim, open the search options and choose Group By > Responsible Party. The total hours lost appear for each party. You can also filter on Client / Engineer, or group by Project or Type.

    Delays grouped by responsible party
    Delays grouped by responsible party.

Crews ​

A crew (or gang) is a team that works together on a project: your own workers led by a foreman, or a subcontractor's team counted by headcount. Crews make the daily report fast: Load Crews adds all their members at once, and the Site App uses them for attendance.

  1. Go to ConstructionSiteCrews and click New.

    List of crews
    The list of crews, with their type and headcount.
  2. For a crew of your own workers: type the name, keep Crew Type = Own Workforce, choose the Project, the Usual Activity, the Trade and the Foreman. Then add the members (employees) in the field under the form. The Headcount is counted for you: the foreman plus the members.

    Own workforce crew
    An own-workforce crew: foreman Keith Byrd and three members, so a headcount of 4.
  3. For a subcontractor's crew: choose Crew Type = Subcontractor, then the Subcontractor company, and type the usual Headcount. You do not list the people one by one.

    Subcontractor crew
    A subcontractor crew of 8 masons.
  4. Save. When a crew moves to another project, change its Project. When a crew is disbanded, archive it: click the ⋮ icon next to its name, then Archive.

TIP

The workers must exist as employees (Employees app) before you can add them to a crew. Their hourly cost, set on the employee, is used to cost their timesheets.

Common messages ​

MessageWhy and what to do
... is submitted: reset it to draft to change it.You tried to change a submitted or approved report. Click Reset to Draft first.
All the crews of ... are already in the report.Load Crews found nothing new to add.
Only site managers and project managers approve daily reports.Your role does not allow approving. Ask your site manager.
Progress is between 0 and 100%.The Progress to Date of a Work Done line must be a percentage.
The quantity done on ... cannot be negativeTo correct a quantity reported too high, reset the earlier report to draft and correct it.